Good news, we are back on track!

Thankfully we have found a solution to our structural dilemma. Our engineer has confirmed that the external leaf of the new cavity walls for bedroom 3 can be supported on 10mm steel plates. Beams D1 and D2 are to be located in line with the existing partition wall above (and with the inner leaf of the cavity walls).

This is great news as not only can we move forwards, but there is minimal change to the existing steel plans and no need for any ground work to reposition the existing support.

I can’t tell you how relieved I am!

Screen Shot 2016-07-22 at 15.40.55Screen Shot 2016-07-22 at 15.44.24


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s